Projects
Find a Project
Universal Project Code - The number assigned to a project when it is entered into the VDOT database. The UPC number remains with the project until completion and provides a good way to identify or check on the status of a project.
Indicates which system, program or mode of transportation the project falls within: Interstate, Primary, Urban, Secondary, Miscellaneous or Public Transportation. Descriptions of the systems are as follows:
  • The Interstate system contains projects identified as being part of the limited-access system of highways that carry route designations such as I-64, I-264, I-464, I-564 and I-664.
  • The Primary system contains projects located along major roadways that carry a route designation of less than 600.
  • The Urban system contains projects located within cities and towns.
  • The Secondary system contains projects located along minor roadways that carry a route designation of 600 or greater.
  • Miscellaneous projects are generally regional in nature and do not clearly fall into one of the above systems.
  • The Public Transportation system contains public transportation projects.
  • The Rail System contains passenger and freight rail projects.
Indicates the locality (or region) in which a project is located, or the agency under which a project is managed.
Scope of Work - Broad category describing the work proposed in the project.
UPC#
Project Name
System
Scope
Cost
Funding
System: Urban
Total Cost: $86,060,614
Total Funding: $75,910,000
System: Urban
Total Cost: $68,352,850
Total Funding: $68,383,566
System: Urban
Total Cost: $68,272,339
Total Funding: $68,272,339
Military Highway WideningMilitary Highway , Route 13
System: Urban
Total Cost: $60,476,095
Total Funding: $60,476,095
Witchduck Road WideningWitchduck Road, Route 190
System: Urban
Total Cost: $60,381,446
Total Funding: $60,381,446
Scope: Transit
Total Cost:
Total Funding: $60,007,000
System: Interstate
Total Cost: $66,754,249
Total Funding: $59,145,303
Midtown Tunnel PPTAMidtown Tunnel, Route 58
System: Primary
Scope: R/W or Eng
Total Cost: $49,951,826
Total Funding: $49,986,196
Deep Creek Bridge ReplacementDominion Boulevard, Route 17
System: Primary
Total Cost: $48,468,000
Total Funding: $47,248,625
System: Urban
Total Cost: $43,824,000
Total Funding: $47,009,769
System: Urban
Total Cost: $42,907,026
Total Funding: $44,855,126
System: Urban
Total Cost: $42,890,459
Total Funding: $42,890,459
System: Primary
Total Cost: $50,503,700
Total Funding: $42,525,487
System: Interstate
Total Cost: $103,210,019
Total Funding: $40,682,537
System: Urban
Total Cost: $55,779,367
Total Funding: $39,830,411
Scope: Transit
Total Cost: NA
Total Funding: $39,153,000.00
Wythe Creek Road WideningWythe Creek Road, Route 172
System: Urban
Total Cost: $41,521,750
Total Funding: $37,572,437
System: Interstate
Total Cost: $40,000,000
Total Funding: $32,500,000
System: Urban
Total Cost: $32,020,000
Total Funding: $32,020,000
Home » TIP Projects